Why we're doing it 

Because of its age and condition, the cenotaph requires repairs and updating to continue supporting commemorative services run by the Hawthorn RSL. Their members are working closely with us on the restoration.

The cenotaph honours those who have served in the Second World War, Korea, Malaya, Borneo and Vietnam Wars. The restoration will be updated to include more recent conflicts where Australian forces served, including:

  • Cambodia 1991–1993
  • Somalia 1992–1993
  • Rwanda 1993–1996
  • East Timor 1999–2013              
  • Afghanistan 2001–2021
  • Iraq 2003–2020 

This work is also part of the St James Park Master Plan and funded through the 2024–25 Council Budget, with support from the Victorian and Australian Governments. 

Status  

Restoration works are expected to start in early September 2025 and be completed by early 2026. 

How you may be impacted

  • St James Park will stay open during this time.
  • The cenotaph and the surrounding work area will be blocked off to the public.  
  • You may hear construction noise on weekdays between 7 am and 3 pm, and some Saturdays (excluding public holidays).
  • 3 parking spaces on Denham Street will be used by the builder’s vehicles. 

Timeline

This project will be delivered in stages:

StageTimeInformationStatus
Stage 1 - Investigation, planning and designJuly 2024

Specialist consultants inspected the cenotaph and developed a condition report.

This report guided what work needs to be carried out to renew and repair the cenotaph.

Complete
Stage 2 - Cenotaph works startEarly September 2025 to early 2026

Works will include:

  • resurfacing weathered stone
  • reapplying gold paint to the lettering  
  • fixing damaged elements
  • replacing the temporary plaque
  • adding theatres of war to the main structure
  • installing power to support ANZAC Day and Remembrance Day events. 
Pending
Stage 3 - Flagpole installationEarly 2026

We're installing 3 flagpoles near the cenotaph to support commemorative services. 

These will fly the Australian, Aboriginal and Torres Strait Islander flags on significant dates. 

Pending

More information

To stay up to date about this project and others being delivered from the master plan, visit our St James Park master plan consultation page

If you have any questions about this project, please contact our Civil Projects team on (03) 9278 4444 or at [email protected]


Was this page helpful?