Work is progressing steadily across the site. Milestones this month include:
Internal wall lining is complete, and ceiling services are nearly complete. Work is continuing on the southern and western external walls, including window glazing.
Internal wall sheeting and ceiling installation is continuing.
Pool tiling, northern wall cladding and brickwork are in progress.
Structural steel framing and roofing is continuing.
Installation of high-level services is continuing.
Preparation for car park construction has started.
In April, we confirmed that Kew Recreation Centre will reopen to the public in July 2027. Read our news article for more information.
Visit our Kew Recreation Centre redevelopment page to see which construction milestones are complete, in progress and coming up across each area of the site.
We’ve added a new section on our redevelopment page to answer commonly asked questions about the project.