Work is continuing steadily with progress across the site. Milestones this month include:
Internal wall lining is almost finished, and ceiling services fit off works are underway. External façade works are progressing well, with the northern section facing Derby Street now complete.
Work on sheeting the internal walls continues, with preparation underway to install electrical, plumbing, heating and cooling services. Ceiling framing is close to completion.
The northern wall lining is advanced with brick façade work now underway. Tiling of the 25 metre pool walls is progressing.
Structural steel framing for the roof canopy facing Coles on Derby Place is now completed and roof installation is now underway.
Earlier this month, we confirmed that Kew Recreation Centre will reopen to the public in July 2027. Read our news article for more information.
Visit our Kew Recreation Centre redevelopment page to see which construction milestones are complete, in progress and coming up across each area of the site.
We’ve added a new section on our redevelopment page to answer commonly asked questions about the project.