Construction is progressing well. This month, the following work was completed or started:
The internal wall linings are finished, and windows are in place on the north and west sides. The timber sports court floors are prepared, and flooring installation has started.
Work is continuing on the outside of the building, mainly on the southern side and cladding areas.
Inside, wall tiling has started in the change rooms.
Wall, ceiling and skylight sheeting is continuing, and the ceiling lining has commenced.
The outside windows are installed. Internal windows will be installed soon.
Structural steel installation has been completed.
Preparation work is continuing.
Visit our Kew Recreation Centre redevelopment page to see which construction milestones are complete, in progress and coming up across each area of the site.
We’ve added a new section on our redevelopment page to answer commonly asked questions about the project.