Construction is progressing well. This month, the following work was completed or started:
Installation of the timber flooring is underway. Work on the external walls is nearly complete.
Rendering of the ceiling is progressing well. Wall tiling works have started.
Installation of the roof sheeting is underway.
Installation of trusses for the roof is complete.
Installation of the structural steel is finished and has been inspected and approved. Installation of the roof is now underway, as well as high-level services work.
Installation of structural steel has started in the western section.
Preparation work is continuing.
Visit our Kew Recreation Centre redevelopment page to see which construction milestones are complete, in progress and coming up across each area of the site.