Construction is progressing well. This month, the following work was completed or started:
The timber flooring is now installed, and court line markings are being applied. Work on the amenities is also moving ahead, with wall and floor tiling complete.
Wall tiling is now finished, and pool tiling will start soon.
Roof installation is complete.
Structural steel is complete, and services installation and roofing is now underway.
The roof is now complete. Installation of services and plaster is underway.
Steel structure installation has started.
Work on the car park is continuing.
Visit our Kew Recreation Centre redevelopment page to see which construction milestones are complete, in progress and coming up across each area of the site.