We are upgrading the facilities at Kew Traffic School in 2020.

Kew Traffic School party room - artist's impression.

Status 

Renewal works have commenced onsite at Kew Traffic School. The facility is now closed to the public. 

Plans for the site have been developed based on feedback from Kew Traffic School users, as well as the need to improve storage for our road safety education program.  

About the project 

Kew Traffic School offers a high quality road safety education program to children in our community. The site will undergo renewal works in 2020 to replace existing, aged facilities. 

Key features of the upgrade include:

  • a new, larger party room with access to a covered outdoor seating area
  • a new bike storage shed with an attached maintenance workshop.

These renewal works will modernise and refresh the facilities and ensure we can deliver an improved experience at this much-loved community facility.

The project will cost $697,500.

Timeline

When Stage Progress update
May 2020 Planning Contract awarded for construction.
June 2020 Construction Kew Traffic School closed to the public and construction commenced.
September 2020 Completion Project expected to be completed.

Consultation

In 2019, over 24,000 children visited the Kew Traffic School. Users of Kew Traffic School told us they would like to see improved facilities, with an emphasis on the party room. Our community’s feedback has helped shape the design of the new party room.

More information

For more information about this project, please contact Nicole Frey, Community Capacity Building Officer on 9278 4014 or at [email protected].