Check if you need Report and Consent for demolition

You need Report and Consent to do any of the following:

  • demolish 100% of a building
  • demolish more than half of the volume of the original building over a three-year time period
  • demolish any part of the façade of a building

facade is an external wall that faces a street or laneway. A facade may include architectural features attached to the wall, such as a verandah or balcony.

If you are unsure as to whether you need Report and Consent for your demolition proposal, seek advice from your Building Surveyor or contact Building Services.

 

Do you need Report and Consent for the proposed demolition?